How long does it take to complete a job?

An average job will take one to three days depending on the condition of the concrete. If new concrete is poured a part of the repair of enlargement prices, the standard concrete will required a 7 days cure before CTi can be applied. As with all exterior surfacing, CTi can not be applied in the rain.